Monday, September 30, 2013
A whole lot of nothing...
As far as taking pictures of stuff, there is a whole lot of nothing to take pictures of. The weather has not cooperated on the weekends( it rained all day Saturday). So, we spent the day at a building material auction, again, and had to pick some of it up Sunday because of the rain. We were able to get several light fixtures,2x4s, locks and door handles,interior doors, and some ceiling joists. There were other things here and there but we only spent $1000, and had two 16 foot trailer loads plus two trucks loaded down twice. We are really hoping the weather will be better this weekend and we can get more done.
Tuesday, September 24, 2013
Finally the concrete is done!
| This time we rented a power screet and it made the job much easier. It was a well spent $60 rental. As well as $60 for the power trowel. |
| The back half of the floor. |
| Finishing up pouring the front half. |
| Ta-da! The front of the house. |
| The back of the house. We figured it all out and after the gravel ,rebar, radient floor tubing and concrete 2400 square foot of concrete floor cost us less than $3 a square foot. |
Sunday, September 15, 2013
Getting ready for concrete pour #2
| My mom , Hannah and I spent the last two days tying and laying out all the rebar between the grain bins and in the area behind the bins. |
| This is a view of the holes that were cut out of the second grain bin. The hole on the right will be the stairwell upstairs. The hole on the left will be part of the utility room. |
Wednesday, September 4, 2013
Cutting out the big doorways
| The window in the second bin and some of the framing in there got done. |
| One of the doorways has a header now. |
| The sunset looking out what will be the front of the house. |
Monday, August 26, 2013
No turning back now...
| The tall studs will be where the stairs will be located. |
| Chris cutting out the windows. There is no turning back now! |
| The windows from the outside. |
| The window on the right is over the kitchen sink. |
Tuesday, August 20, 2013
We have concrete!
The first pour of concrete was done over the weekend. Chris has started to mark out where the windows will go and the doorway openings to the living room from each bin. The spray paint boxes are the areas that will be cut out of the grain bin.
| The box in this picture will be the kitchen window over the sink. |
| This is where the cut out for the stair well leading up to the girls' rooms will be |
| The door area will be cut out for access to the rest of the house. And the will be a window on the side too. |
| This is bin number two. This cut out will be for the stair well to the master bedroom/bath. |
| Where the second cut out starts there will be a wall and that area will be the laundry/utility room. |
| Our youngest daughter thinks the concrete is great. She has her own skating rink any time she wants!! |
Wednesday, August 14, 2013
Before and after tin tiles
| This will be the tile on the wall of the kitchen( subject to change , but that is the plan) |
| After cleaning one time with oven cleaner. Oven cleaner is what I read on the internet to be the best at removing some paint and not damaging the tin underneath. |
| After cleaning twice with oven cleaner. I did not think there was yellow under all that green. I'm not sure I like the yellow but we will figure it out later. At least all of the loose paint is off. |
| Two of the other kinds of tile. The white one is the same as the one underneath it. The long white piece is crown moulding. |
| The orange will be a ceiling but haven't yet decided where to put it. The white crown moulding goes with it. |
| After one round of oven cleaner. |
| After the second cleaning. Now just a few hundred more pieces to clean! We are still figuring out if we will end up painting over them or just clear coating them. |